PUBLIC NOTICE: Water Main Improvement Project Date: April 24, 2025
Project Name: Water Distribution System Improvements – Sully, Iowa – 2025
Dear Residents and Businesses,
Shane Poe Construction is scheduled to begin water distribution system improvements in early May 2025 and finish construction in late September 2025. The project primarily includes replacing aged cast iron water main piping with new PVC piping and reconnecting water service lines. The majority of the water piping will be installed by boring a hole underground and then pulling the piping into the hole. This style of construction only requires digging between water main sections and at service line connections; grass, sidewalks and pavement at the connection points will be replaced. This project will improve the reliability and efficiency of the water system.
Approximate Work Locations: 3rd Ave (1st to 2nd St), 2nd St (3rd to 4th Ave), 2nd St (east of 9th Ave), 5th Ave (2nd to 4th St), 7th Ave (2nd to 5th St), 8th Ave (4th to 8th St), 3rd St (5th to 7th Ave), 4th St (4th to 8th Ave), 5th St (5th to 7th Ave); see link below for project location map
Normal Construction Hours: Monday through Thursday, 7:00 AM to 7:00 PM; work on Friday is allowed, but not currently expected
Traffic Impacts: Roads may be closed to through traffic and temporary lane closures are anticipated. Please follow posted signs and use alternate routes when possible.
Water Service Interruptions: Temporary water shutoffs will occur when connecting new water mains and service lines. Shane Poe construction will provide notification 48 hours in advance of any scheduled service disruptions; interruptions will typically be less than 4 hours.
If you have questions or concerns about the project, please contact City Hall at 641-594- 3493. Thank you for your patience and cooperation during this project.
Sincerely,
Sully City Council